Week 9: Construction and Purchase of Solar Panels Supporting Structure (3/22-3/28)
Plan on logistics of ordering materials was completed. On March 26, Monday, less than a dozen different parts manufactured by Unistrut will be purchased at Lord & Sons, inc., in North San Jose. Lord & Sons, inc., is one of the Unistrut's distributors in the Bay Area. A 26-feet-long U-Haul truck will be rented to allow the handling of the 20-feet-long c-channels. All the parts picked up from Lord & Sons, inc. will be unloaded to Spartan Superway Design Center on the same day. Purchase of gutter, gutter cover, and electrical elements will be purchased on the same day. On March 27, Tuesday, building the structural supporting system of solar panels will be started.
Subscribe to:
Post Comments (Atom)
The discovery channel has recorded footages of Spartan Superway. Final presentation for full-scale solar team was held in E135 at 11:30 AM. ...
-
A method to attach the gutter system on solar rack structure was devised. It would allow a constant water flow from the tarps which will be...
-
The discovery channel has recorded footages of Spartan Superway. Final presentation for full-scale solar team was held in E135 at 11:30 AM. ...
-
This week, sub-teams for full scale and half scale parts of the Spartan Superway had a presentation. Each team's presentation helped our...