Friday, May 11, 2018

Week 16: Final Presentation of Spartan Superway

The discovery channel has recorded footages of Spartan Superway. Final presentation for full-scale solar team was held in E135 at 11:30 AM. the gutter system has been demonstrated in the presentation. The team has been able to complete the prototype that is quite identical to what was designed on Solidworks.

Friday, May 4, 2018

Week 15: Gutter attaching solution (5/3-5/9)

A method to attach the gutter system on solar rack structure was devised. It would allow a constant water flow from the tarps which will be placed between c-channels and solar panels. Solar Clamps and solar panels were attached to c-channels to test the rigidity of the structure. Electrical components assembly and water gutter system will be completed within a week.

Week 14: Completion of main structure(4/26 - 5/2)



Longitudinal c-channels were cut to 3 meters and attached to the vertical beam sections using Unistrut's 4-hole 90-degree bracket. Heat shrink with 12 gauge ring terminals, copper wires, were power connector contacts were completed. It was connected to three of 12 volts batteries individually. Solar panels, charge controller, and battery were connected to test the charge controller's condition.







Week 13: Gusset plates on "Rib" design (4/19 - 4/25)

Cutting process of angled c-channels was completed. 16 Gauge sheet metal plates in 10" by 10" were attached to the vertical supporting structure of the solar rack. Self-tapping screws were utilized to put the gusset plates and c-channels together. Bogie Team member Dan Espinosa's 3 cordless drills were borrowed for a faster construction time.

Wednesday, April 11, 2018

Week 12: Presentation 2 on April 11th (4/12 - 4/18)

Presentation 2 was delivered by the solar team on April 11th. CFD results and its hand calculation was advised to be modified. A number of angled cuts of c-channels will be conducted over the weekends. 16Ga sheet metal, which was purchased at Acosta sheet metal manufacturing, will be ordered in the quantities of 24 in the dimensions of 10" by 10". Batteries, charge controllers, parallel y-connectors, extension cables, and MC3 to MC4 converter have been purchased. Wires, gutter, and wooden fake panels will be purchased as well.

Tuesday, April 10, 2018

Week 11: Electrical Components Configuration & Gusset Plates Option (4/5-4/11)

Electrical components have been configured with different iterations. It will be finalized by the end of the second week of April. Fuses will be purchased on Renogy. Batteries, Charge Controllers and 12 AWG copper wires will be purchased on Amazon. Solar panels extension cables with 12 AWG will be purchased on general solar supply. The configuration is shown below.
Acosta Sheet Metal Manufacturing offered reasonable pricing options as well as custom sizing options using laser cutter upon our needs with extra charges. Two different sheet metals were purchased and tested: 16Ga and 18Ga. Since 16Ga is more rigid than 18Ga due to its thickness, it has been selected as the gusset plates materials. 24 of 10" by 10" 16Ga galvanized steel sheet metal will be ordered by the end of the second week of April.

Wednesday, April 4, 2018

Week 10: C-Channels & Solar end clamps handling & Cutting C-Channels & CFD(3/29-4/4)

Throughout the spring break, multiple tasks have been completed. On 3/26/2018, 20 of 26-feet-long U-Haul truck was rented to load and unload the 20-feet-long c-channels from Lord&Sons, Inc. Also, gutter and gutter guards/covers were purchased at Lowe's. On Tuesday, the solar extension cables and solar end clamps were purchased. For the rest of the spring break, the spare scrap metals in the shop were used for practice cutting. Few of straight sections of c-channels have been cut as well. Also, the CFD was conducted using Ansys on solar panels regards to the wind lift encompassing the lift and drag coefficients.

Sunday, March 25, 2018

Week 9: Construction and Purchase of Solar Panels Supporting Structure (3/22-3/28)

Plan on logistics of ordering materials was completed. On March 26, Monday, less than a dozen different parts manufactured by Unistrut will be purchased at Lord & Sons, inc., in North San Jose. Lord & Sons, inc., is one of the Unistrut's distributors in the Bay Area. A 26-feet-long U-Haul truck will be rented to allow the handling of the 20-feet-long c-channels. All the parts picked up from Lord & Sons, inc. will be unloaded to Spartan Superway Design Center on the same day. Purchase of gutter, gutter cover, and electrical elements will be purchased on the same day. On March 27, Tuesday, building the structural supporting system of solar panels will be started.

Week 8: Bi-Weekly Meeting #1 with Futran (3/15-3/21)

On March 21, 2018, Wednesday, the first official bi-weekly meeting was held with Gary Shaver who represents Futran in South Africa. Reviews on the designs and computations regard to solar panels, supporting structures, and electrical components was completed during the meeting. The meeting agenda which was submitted few days before March 21 was used as a reference during the meeting. The team has provided details on what the team will be working on during the Spring break. It includes the following: purchase and construction of the main structural support system for solar panels. About one-third of goals need to be accomplished by the end of April.

Week 7: Scope of Work & Presentation in ENGR189(3/8-3/14)

A presentation on Global Economy and Social Impacts was held in ENGR 189 on March 14, 2018, Wednesday. It was held before the senior project session in Superway design center. Scope of work was temporarily completed to describe what specifications will be accomplished. Gutter Helmet, the gutter manufacturing company which holds a patented design and its name, was contacted. The sales department informed that the Gutter Helmet only sells the gutter as a whole installation package instead of selling the parts only. Thus, 3D modeling of gutter was done and possible replacements were researched on Lowe's website. One of the viable options for gutter and gutter cover would be parts made from Amerimax which sells at most of Lowe's locations.

Week 6: Bill of Materials & Gutter Design (3/1-3/7)

Different designs of gutter and gutter cover was researched for this week. For the most days, Bill of Materials for all the necessary components for the solar team was completed with comprehensive research. Electrical components were also included in the Bill of Materials with the consideration of different arrangements of solar panels. The budget plan includes a 6m long module of solar panels supporting structure.

Week 5: Presentation 1 & Design Changes (2/22-2/28)


Presentation 1 was presented on 21st of February, Wednesday. Dr. Furman provided feedbacks on the designs on supporting and gutter structures. Possible methods to accomplish a spherical solar panels placement were advised by Dr. Furman after the presentation. Used solar panels were picked up for free at Cinnamon Solar in Campbell after several phone calls to local solar companies were made. Electrical requirements and the related components were briefly introduced along with manipulations of solar panels arrangements.

Week 4: Presentation 1 Preparation (2/15-2/21)

Electrical components were learned by the fellow project member, Dan Espinosa, who has had experience in the industry for about 20 years. Comprehension of the selecting a correct inverter, charge controller, battery, and extension cables were completed thanks to his help. Different iterations of the arrangement of solar panels were conducted so that an optimal battery could be selected and purchased in a timely manner. Extension cables to connect solar panels the team has obtained were found as well.
In terms of design, gutter and gutter cover were researched to use it as a mean to collect water. Water repellent materials would be attached along with solar panels so the water could flow down to gutter which will be placed at each longitudinal sides of the complete structure. To strengthen the supporting structure, gusset plates would be considered to be attached on each flat side of the structure upon Dr. Furman's advice.
The preparation for presentation 1 was conducted for the week. A comprehensive survey of solar team's work would be included in it.
Also, a presentation on how to create effective presentations was held in ENGR 189 on February 14, 2018, Wednesday. It was held before the senior project session in Superway design center.

Wednesday, February 14, 2018

Week 3: Design Change II (2/8-2/14)

This week, another design iteration which is close to an ideal shape the team was aiming for. The design was to have the standard-sized solar panels attached on top of the supporting structure. Also, less amount of materials will be used for the new design the team has developed.

Wednesday, February 7, 2018

Week 2: Design Change (2/1-2/7)

Our team was required to change the design which includes some new features. We are currently working in changing the support design in an elliptical shape. The team would be incorporating options to make the structure durable and environmentally friendly.

Wednesday, January 31, 2018

Week 1: Spring 2018 (1/25-1/31)

The faculty and advisors of Spartan Superway requested the change in design due to the overall cost reduction in building prototype. As a follow-up, the solar team made a radical design change, which helped the cost to drop a lot.

The supporting structure materials including clamps and straight steel sections were researched again to make the entire structure lighter and cost-efficient. Also, since the length of the one module of the prototype is being shortened, the required number of solar panels will be dropped as well.

I have made a list of things that will be discussed in the full-scale teams meeting with advisors of the Spartan Superway that will be held on January 31st, 2018. One of the factors that have to be confirmed is the width dimension of the entire canopy design as it remained in the midst of confusion.

Tuesday, December 5, 2017

Week 15: Presentation 3

On November 29, 2017, our sub-team has held a presentation on the prospective design draft for solar panels racking system and the truss structure for it. Our group was able to reduce the deflection of the beam that will be in the truss structure down to 6 cm, which is very low compared to the second presentation. Our group needs to find a galvanized steel stud with 10 inches in depth to decrease the deflection of the beam. Also, our team will find out the Bill of Materials for the C shape steel stud, self-drilling screws.

Wednesday, November 8, 2017

Week 10: Lockheed Martin Presentation Preparation

Our team has been preparing the presentation slides for Lockheed Martin Presentation. Also, we are in the process of finalizing our design based on solar panels that are available in our shop. The materials that will be used for the racking system would be sheet metal.

Wednesday, November 1, 2017

Week 9: Second Presentation and Possible Design Change

This week, the team held a presentation with one of the designs for solar panels rack. Dr. Furman provided feedback on what to improve on with our designs as well as what to consider about. The team may change the racking design after consulting with Dr. Furman on 11/1 Wednesday.

Wednesday, October 18, 2017

Week 8: Further Discussion on Design Iterations

This week, each member in the sub-team came up with 2 design iterations. The team is trying to focus on two design iterations created by Tan as well as a design suggested by Nicolas. First type is a shell shape, one of organic shapes, to create an aesthetic design. Paul has demonstrated how to create the shape using Solidworks during the weekly team meeting hours on October 10th Wednesday. The first one is the ideal design the team would like to build. Second iteration is design involving canary. Use cables to make holes on canary to keep the structure in place without using truss structure. Third design, which is brainstormed by Nicolas, focuses on the lightweight of the entire racking system. Wires or cables will be used in across its design, which has an arch shape. This will replace the truss structure as well as increase the ease of installation on top of the guideway.

The discovery channel has recorded footages of Spartan Superway. Final presentation for full-scale solar team was held in E135 at 11:30 AM. ...